MANILA: The Philippines' Economy and Development Council, chaired by President Ferdinand Marcos Jr, approved on November 11 a six-month extension for Phase 1 of the Metro Manila Flood Management Project, moving the deadline from December 2, 2026 to May 31, 2027, Philstar reported. Seven of the 38 planned pumping stations remain unfinished. The Presidential Communications Office said scope and cost were unchanged and called it "the project's second and final extension". State auditors have found 28 of the metropolitan authority's 119 pumps unserviceable, Astig.ph reported.

Philstar, Nov 12 - Astig.ph