BOGOTA: Mayor Carlos Fernando Galan said on October 4 that Metro Line 1 stands 82.33% complete against a planned 86.79% - about 4.5 points behind on stations, communications systems and public space - and the city has asked the builder to add workers. Trial runs remain targeted for September 2027, paid service for March 2028, the date announced to fanfare only weeks ago.

Rio Times, Oct 4